Abilene TX Campus (Stargate Site 1) Buildout Tracker
| Attribute | Detail | Status / Timeline |
|---|---|---|
| Total campus power | 1.2 GW total power capacity | First two buildings operational, six under construction (Jun 2026); second phase expected to complete by end of 2026 |
| Buildings / floor area | 8 buildings, ~4 million sq ft | Six buildings added in the Mar 2025 expansion |
| Phase 1 (first two buildings) | 200+ MW, ~980,000 sq ft | Energized and live on Oracle Cloud Infrastructure (announced 30 Sep 2025) |
| GPU capacity per building | Up to 50,000 NVIDIA GB200 NVL72s | Design spec, on a single integrated network fabric |
| GPU capacity at full buildout | Hundreds of thousands of GPUs | On a single integrated network fabric at completion of the eight-building campus (Sep 2025) |
| Commercial structure | Built to support Oracle Cloud Infrastructure; Crusoe says OpenAI trained Astra at the campus | Stargate's flagship data center campus; Crusoe designs, builds and operates |
| First GB200 racks delivered | Oracle began delivering NVIDIA GB200 racks | June 2025 |
| Construction workforce | ~2,000 daily workers (Mar 2025); ~3,000 (May 2025) | Expected to reach nearly 5,000; construction commenced June 2024 |
| Adjacent Microsoft campus | 900 MW, two buildings of 336 MW critical IT load each, with an onsite power plant | First building expected energized in mid-2027; projected site total 2.1 GW |
Crusoe Cloud Growth Metrics and Marquee Customers
| Metric / Customer | Value | Notes |
|---|---|---|
| Cloud ARR growth (2025) | 150% YoY | Crusoe-stated; driven by adoption from AI-native companies |
| Added total contract value (2025) | ~17x YoY | Crusoe describes deep, multi-year commitments |
| Crusoe Cloud bookings (first 3 quarters 2025) | 5x vs prior year | Bookings, not recognized revenue |
| New logos (2025) | ~70% increase | New customer accounts added |
| Crusoe Cloud bookings (2026 year to date) | 20x+ YoY | As of Crusoe's 17 Sep 2026 release |
| Crusoe Managed Inference contracted ARR | Over $100M | Launched in late 2025; stated 17 Sep 2026 |
| Marquee customers | Cursor, Decart, Fireworks, Odyssey, Together AI, 1X, Yutori, Cognition, Figure, Perplexity, Codeium | Accounts Crusoe names in its releases and blog (Dec 2024 to Sep 2026) |
Crusoe Flared-Gas / Stranded-Energy Origin Metrics
| Metric | Figure | As of / Notes |
|---|---|---|
| Flare gas converted (annual) | Over 10.4 billion cubic feet | 2024; otherwise-flared wellhead gas |
| Power generated from flared gas | ~1.3 TWh | 2024, supplying 87% of Crusoe's total electricity needs; over 635,000 MWh in 2023 |
| Deployed capacity | Over 200 MW | 2023, across Crusoe's Cloud and bitcoin mining businesses; about one-third of Crusoe Cloud's 2023 energy was DFM-powered and two-thirds was 100% renewable energy at third-party data centers |
| DFM project deployments | 33 in the U.S. (12 new in 2023) | 2023 impact report |
| Footprint of the bitcoin mining business | Seven states and two countries | Colorado, North Dakota, Montana, Wyoming, New Mexico, Utah, Texas and Argentina (Mar 2025) |
| Bitcoin-mining fleet divested | 425+ modular data centers, 250+ MW | NYDIG announced plans to acquire it on 25 Mar 2025; terms not disclosed; about 135 Crusoe employees would join NYDIG |
| Cumulative flaring avoided (Mar 2025) | Nearly 22 billion cubic feet | Since 2018; 2.7 million metric tons of greenhouse gas emissions mitigated |
| Lifetime of the DFM business | More than 27 billion cubic feet captured; 3.3 TWh generated | 3.4 million metric tons of CO2-equivalent avoided; business divested in 2025 (2025 impact report) |
Crusoe Funding, Valuation, and Project Debt Stack
| Round / Facility (date, lead) | Amount Raised | Valuation (as stated by Crusoe) | Notable Participants |
|---|---|---|---|
| Series A (2019) | $27.5M (Form D amount sold) | n/a | Not named by Crusoe |
| Series B (2021-04, Valor Equity Partners) | $128M | n/a | Valor (lead), Lowercarbon, DRW Venture Capital, Founders Fund, Bain Capital Ventures, Coinbase Ventures, Polychain; plus a non-dilutive $40M project financing facility from Upper90 |
| Series C (2022-04, G2 Venture Partners) | $350M | n/a | G2 (lead), Valor, Lowercarbon, Polychain, Bain Capital Ventures, Founders Fund; new investors included Engine No. 1, Felicis and Mitsui; plus credit facilities expandable up to $155M |
| Series D (2024-12, Founders Fund) | $600M | $2.8B | Founders Fund (lead), Fidelity, Long Journey Ventures, Mubadala, NVIDIA, Ribbit Capital, Valor |
| Series E (2025-10, Valor + Mubadala Capital) | $1.375B | Over $10B | Valor + Mubadala Capital (co-leads), NVIDIA, Fidelity, Founders Fund, Franklin Templeton, Spark Capital, Tiger Global; Blue Owl funds expected to join in a later closing |
| Series F (2026-09, Atreides + Mubadala Capital + Valor) | $3.9B (initial closing of an anticipated round) | $30.9B post-money | Atreides, Mubadala Capital, Valor (co-leads), Founders Fund, GIC, NVIDIA, Qatar Investment Authority, Radical Ventures, TPG; Form D (17 Sep 2026): $3.11B sold of a $3.90B offering, including certain previously issued SAFEs |
| Abilene joint venture (2024-10 and 2025-05, Blue Owl) | $3.4B (phase 1, 206 MW); $15B for the 1.2 GW campus | n/a (project financing) | Blue Owl, Primary Digital Infrastructure, Crusoe |
| Upper90 credit facility (2025-03) | ~$225M | n/a (credit facility) | Upper90 (lead), British Columbia Investment Management Corporation, FS Investments, King Street, Liberty Mutual Investments, ORIX USA; for NVIDIA GPUs and cloud infrastructure |
| Brookfield credit facility (2025-06) | $750M | n/a (credit facility) | Brookfield Asset Management |
| Neuberger facility (2026-10) | $700M | n/a (credit facility) | Neuberger Specialty Finance; secured by recently ordered power generation equipment |