Partial operating KPIs
This page has 2 company-specific operating KPI charts. A sourced floor is 4. Sector membership does not count.
Holtec Palisades DOE LPO Commitment
DOE LPO ($M)
Holtec International: Palisades Nuclear Plant Restart Milestone Tracker
| Milestone | Target Date | Status | Notes |
|---|---|---|---|
| Hyundai E&C teaming agreement for SMR design and delivery | Nov 2021 | Complete | Agreement to complete the SMR-160 standard design and deliver projects worldwide (Holtec, Nov 22 2021); the S-1/A describes Hyundai E&C as the exclusive EPC delivery partner for the SMR-300 program |
| Entergy permanent shutdown | May 2022 | Complete | Permanently ceased power operations May 20 2022 (NRC, Federal Register Jul 29 2025) |
| Holtec acquisition close | Jun 2022 | Complete | Closed under a Jul 2018 agreement; Holtec says it decided to pursue a restart shortly after obtaining the site (S-1/A) |
| Restart regulatory path outlined to NRC | Mar 2023 | Complete | Letter to the NRC dated Mar 13 2023; exemption request followed on Sep 28 2023 |
| NRC license restoration requests | 2023-2024 | Complete | Exemption request Sep 28 2023; license transfer application Dec 6 2023; license amendment requests Dec 14 2023 to May 24 2024 |
| DOE LPO conditional commitment | Mar 2024 | Complete | Conditional commitment of up to $1.52B announced Mar 27 2024; loan closing announced Sep 2024 under a guarantee agreement dated Jul 31 2024 |
| Steam generator + RPV inspections | 2024-2025 | In progress | Mothballed equipment requires extensive inspections + refurbishment |
| Steam generator replacement decision | 2024-2025 | Replacement confirmed; new SGs installed | Major capex item; significant project risk if scope expanded |
| NRC license restoration approved | Target 2025-Q4 to 2026-Q1 | Complete (Jul 2025) | NRC approved the licensing package to reauthorize power operations |
| Returned to operational status | 2025 | Complete (Aug 25 2025) | Palisades moved from decommissioning to operations status; Holtec calls it the first time a US nuclear plant has done so (Holtec, Aug 26 2025); authorized to receive nuclear fuel |
| Fuel load | Target 2026 | Fuel loading began Aug 30 2026; a fuel assembly tilted during loading and was recovered Oct 21 2026 | Holtec recovered the assembly with a purpose-built Fuel Movement Device under an NRC-approved license amendment; existing PWR fuel design (~5% LEU) |
| First criticality | Target 2026 | Subject to fuel load + final inspections | Restart milestone |
| Commercial Operations Date (COD) | Target 2026 (Holtec stated) | Not yet in service; Holtec says on Oct 29 2026 that fuel loading, testing and startup work remain | Power purchase agreements require the site to be in service by March 2027, or either party may terminate (S-1/A) |
| Editorial. Why this matters | Palisades is the second major US nuclear restart story alongside CEG Crane. DOE's $1.52B loan guarantee (conditional commitment Mar 27 2024; closing announced Sep 2024) reflects federal support for the restart path. Marquee question: does Palisades return to service before the March 2027 date in its power purchase agreements, or does it slip beyond it + erode the company's stated path to first revenue + SMR-300 commercialization narrative? |

Holtec International in Nuclear
KPI data tables
Holtec International operating metrics behind the KPI charts, newest period first (up to 24 periods per chart). Periods use each company's own fiscal labels where the source does; each table names its source.
| Period | DOE LPO ($M) |
|---|---|
| 2025 additional release (cumulative) | 1,603 |
| 2024-03 conditional commitment | 1,520 |
Source: src/data/kpis/holtec-international/palisades-restart-milestone-tracker.json