National Grid operating metrics behind the KPI charts, newest period first (up to 24 periods per chart). Periods use each company's own fiscal labels where the source does; each table names its source.
| Period | UK Electricity Transmission | UK Electricity Distribution | New York | New England | National Grid Ventures | UK Electricity System Operator | Other |
|---|---|---|---|---|---|---|---|
| FY 2026 | 4,372 | 1,617 | 3,428 | 2,043 | 109 | 0 | 7 |
| FY 2025 | 2,999 | 1,426 | 3,289 | 1,751 | 378 | 0 | 4 |
| FY 2024 | 1,912 | 1,247 | 2,654 | 1,673 | 662 | 85 | 2 |
Source: National Grid Full Year Results presentation for the year ended 31 March 2026, Capital investment table at actual exchange rates (FY 2026 and FY 2025): https://www.nationalgrid.com/document/576631/download. Full Year Results presentation / Annual Report for the year ended 31 March 2025, capital investment at actual exchange rates (FY 2025 and FY 2024): https://www.nationalgrid.com/document/559906/download and https://www.nationalgrid.com/document/560311/download.
| Period | UK Electricity Transmission | UK Electricity Distribution |
|---|---|---|
| FY 2026 | 23,847 | 13,139 |
| FY 2025 | 20,570 | 12,235 |
| FY 2024 | 18,388 | 11,497 |
Source: National Grid Full Year Results presentation for the year ended 31 March 2026, Detailed RoE and Regulated Financial Position for UK Electricity Transmission (closing RAV £23,847 million) and UK Electricity Distribution (closing RAV £13,139 million), with FY 2025 comparatives £20,570 million and £12,235 million: https://www.nationalgrid.com/document/576631/download. Full Year Results presentation for the year ended 31 March 2025, RAV table (FY 2024 closing RAV UK ET £18,388 million, UK ED £11,497 million): https://www.nationalgrid.com/document/559906/download.
| Period | UK RAV | US rate base |
|---|---|---|
| FY 2026 | 36,986 | 29,452 |
| FY 2025 | 32,805 | 27,345 |
| FY 2024 | 30,310 | 24,527 |
Source: National Grid Full Year Results presentation for the year ended 31 March 2026, asset growth and regulatory gearing tables (UK RAV and US rate base as at 31 March): https://www.nationalgrid.com/document/576631/download. Full Year Results presentation for the year ended 31 March 2025, RAV / rate base table (FY 2024 and FY 2025): https://www.nationalgrid.com/document/559906/download. Form 20-F for the year ended 31 March 2026 (asset growth narrative): https://www.sec.gov/Archives/edgar/data/1004315/000100431526000006/nggtf-20260331.htm.
| Period | NIMO Electric (upstate NY) | KEDNY (downstate gas) | Massachusetts Gas | KEDLI (Long Island gas) | Massachusetts Electric (incl. transmission) | New England Power (FERC) | NIMO Gas (upstate NY) | Other FERC |
|---|---|---|---|---|---|---|---|---|
| FY 2026 | 10,000 | 8,025 | 5,867 | 4,760 | 4,399 | 3,271 | 2,569 | 76 |
| FY 2025 | 9,232 | 7,212 | 5,408 | 4,439 | 3,766 | 2,938 | 2,266 | 58 |
| FY 2024 | 8,317 | 6,454 | 4,759 | 4,149 | 3,541 | 2,646 | 1,765 | 48 |
Source: National Grid Full Year Results presentation for the year ended 31 March 2026, Detailed RoE and Regulated Financial Position for New England and New York (rate base $ million as at 31 March 2026 and 2025): https://www.nationalgrid.com/document/576631/download. Full Year Results presentation for the year ended 31 March 2025, same tables (FY 2024 comparatives): https://www.nationalgrid.com/document/559906/download.