Tokamak Energy ST40 Ion Temperature Milestone
Ion temperature (million C)
Tokamak Energy: ST40 + ST80-HTS Development Milestone Tracker
| Milestone | Target Date | Status | Machine + Notes |
|---|---|---|---|
| ST40 begins operating | 2017 | Complete | Tokamak Energy says ST40, which it calls the world's highest-field spherical tokamak, was designed, built and in operation in 2017 (Tokamak Energy About page) |
| ST40 100M C plasma temperature | Mar 2022 | Achieved (Mar 2022) | Marquee scientific milestone; published Nuclear Fusion journal |
| ST40 sustained plasma + stability validation | 2022-2024 | Complete | Continued ST40 operations through 2024 |
| ST40 record results + $52M upgrade programme | 2025-2026 | Record results announced Dec 2025; upgrade shutdown began late 2025 and runs through most of 2026 | $52M upgrade with US DOE + UK DESNZ covering lithium systems and RF heating |
| STEP programme magnet systems partner | Mar 2026 to Mar 2029 | Awarded (GBP 70M contract) | UK Fusion Energy appointed Tokamak Energy for magnet architecture, tokamak systems engineering and plasma facing integration |
| ST80-HTS site (Culham Campus, UKAEA) | Announced Mar 2023 | Site announced | Tokamak Energy said it will build ST80-HTS at the UK Atomic Energy Authority's Culham Campus (Tokamak Energy, Mar 28 2023) |
| ST80-HTS magnet manufacturing | 2024-2026 | In progress | REBCO-based HTS coil set; analogous to CFS SPARC magnets |
| ST80-HTS construction completion | Target 2026 | Not announced as complete as of Jul 2026; de-emphasized | ST80-HTS no longer appears in how the company describes its route to a power plant, suggesting the device has been deprioritized or dropped |
| ST80-HTS first plasma | Target 2027 | Uncertain following the de-emphasis of ST80-HTS | Company focus has shifted toward the ST40 upgrade and the STEP magnet partnership |
| Pilot plant design programme | Oct 2024 to Aug 2026 | Design only: Tokamak Energy will not construct the plant | Initial designs presented Oct 7 2024 under the US DOE Milestone-Based Fusion Development Program (800 MW of fusion power, 85 MW net electricity); an 11-paper collection published Aug 18 2026 (Tokamak Energy, Oct 15 2024 and Aug 18 2026) |
| Editorial. Why this matters | Tokamak Energy is the UK-led spherical tokamak + HTS magnet developer + a structural alternative to CFS in the HTS-tokamak race. Its pilot plant is now a design only: on Aug 18 2026 Tokamak Energy said it will not construct the plant. Marquee question: does the UK STEP program, where Tokamak Energy is magnet systems partner, become its route to a commercial plant through the 2030s-2040s? |

Tokamak Energy in Nuclear
KPI data tables
Tokamak Energy operating metrics behind the KPI charts, newest period first (up to 24 periods per chart). Periods use each company's own fiscal labels where the source does; each table names its source.
| Period | Ion temperature (million C) |
|---|---|
| 2022-03 ST40 | 100 |
| 2021 | 0 |
Source: src/data/kpis/tokamak-energy/st40-st80-milestone-tracker.json