$4B
Total raised after the $1B equity raise announced Jul 30 2026
HTS Magnet Test
20 Tesla
Sep 2021 TFMC test; CFS and MIT call it the world's strongest HTS magnet
SPARC Q>1 Target
2027
CFS says SPARC will produce more energy from fusion than it needs to power the process
Google ARC PPA
200 MW
Jun 30 2025; CFS expects power on the grid in the early 2030s
Funding History
Total raised: $4B (CFS, Jul 30 2026) · Latest valuation: Undisclosed
| Round | Date | Amount | Valuation | Key Investors |
|---|---|---|---|---|
| Seed / Series A | 2018-2020 | ~$215M | - | Breakthrough Energy VenturesEniThe EngineKhosla Ventures+2 more |
| Series B | Dec 2021 | More than $1.8B | - | Tiger Global (lead)Bill GatesCoatueMarc Benioff+10 more |
| Series B2 | Aug 2025 | $863M | - | Tiger GlobalCoatueNVIDIA (NVentures)Eni+5 more |
Product Specifications
| System | Type | Status |
|---|---|---|
| SPARC | Compact tokamak (50 MW thermal, Q>1 target) | Under construction at Devens, MA; Q>1 targeted for 2027 |
| ARC | Commercial pilot plant (about 400 MW of electricity) | Site announced Dec 17 2024 in Chesterfield County, VA; CFS expects power on the grid in the early 2030s |
| HTS Magnets | High-temperature superconducting magnet family (20 T capable) | Production. CFS is the world's leading HTS-magnet manufacturer for fusion |
| Fuel Cycle / Tritium Breeding Blanket | ARC blanket and tritium handling R&D | R&D |
Partnerships & Investors
Continuous research collaboration; SPARC physics validation work runs at MIT PSFC alongside Devens build.
Investor since 2021 (Series B) and among the Series B2 investors; 200 MW ARC PPA announced Jun 30 2025, with an option on power from additional ARC plants.
Bill Gates joined as a new investor in the Dec 2021 Series B; Breakthrough Energy Ventures is named as an existing investor in the Jun 2019 Series A release.
Italian oil major; announced as a $50M investor when CFS launched in Mar 2018, and signed a power purchase agreement for part of the first ARC plant's output.
Norwegian state energy company; Series B + B2 investor; strategic energy-transition positioning.
Dominion Energy Virginia owns the ARC Chesterfield site and provides non-financial collaboration including development and technical expertise and leasing rights.
Milestone-based Public-Private Partnership program participant; HTS magnet and fuel-cycle research grants.
Key Milestones
Company Founded
MIT announces on Mar 9 2018 a collaboration with a new private company, Commonwealth Fusion Systems, which says it has attracted a $50M investment from Eni; CFS says it spun out of MIT's Plasma Science and Fusion Center in 2018, and its releases name Bob Mumgaard (CEO), Dennis Whyte and Brandon Sorbom as co-founders
20 Tesla HTS Magnet Test
CFS and MIT's Plasma Science and Fusion Center announce on Sep 8 2021 the test of what they call the world's strongest HTS magnet, which reached a sustained magnetic field of more than 20 tesla; CFS later calls it the Toroidal Field Model Coil (TFMC)
Series B at $1.8B
CFS announces on Dec 1 2021 that it closed more than $1.8B in Series B funding, led by Tiger Global Management, with new investors including Bill Gates, Google, John Doerr and Marc Benioff's TIME Ventures
Devens MA Campus Opens
CFS selects a 47-acre site in Devens, MA on Mar 3 2021 for its fusion campus and officially opens the nearly 50-acre campus on Feb 10 2023, which houses its headquarters, magnet manufacturing facility and the SPARC facility, with SPARC still under construction
Chesterfield VA ARC Site
CFS announces on Dec 17 2024 that it will build its first ARC plant, about 400 MW of electricity, at the James River Industrial Center in Chesterfield County, VA; Dominion Energy Virginia, which owns the site, provides non-financial collaboration including development and technical expertise and leasing rights, and CFS says it will finance, build, own and operate the plant
Google ARC PPA
Google and CFS announce on Jun 30 2025 a power purchase agreement for 200 MW from CFS's first ARC plant in Chesterfield County, VA, which CFS expects to put power on the grid in the early 2030s; Google also gets an option to buy power from additional ARC plants and increases its stake in CFS, on undisclosed terms
Series B2 ($863M)
CFS announces on Aug 28 2025 an oversubscribed $863M Series B2 round, with Google, NVentures (NVIDIA's venture arm) and a Japanese consortium led by Mitsui and Mitsubishi among the investors, to complete SPARC and progress the first ARC plant in Virginia; CFS says it has raised close to $3B to date. A further $1B equity raise announced Jul 30 2026 brings the total raised to $4B
SPARC Magnet Delivery
CFS says it shipped the first of SPARC's 18 toroidal field magnets, a 24-ton magnet, from its Devens factory to the SPARC facility in Dec 2025; its Jan 8 2026 six-month update says CFS has also received the first half of the SPARC vacuum vessel
SPARC Q>1 Demonstration
CFS says SPARC, at its Devens campus, will produce more energy from fusion than it needs to power the process (Q>1) in 2027
ARC Commercial Plant Online
CFS says its first ARC plant in Chesterfield County, VA, which will generate about 400 MW of electricity, is on track to put power on the grid in the early 2030s; Google and Eni signed power purchase agreements for more than half of its output, and Google's agreement covers 200 MW
KPI data tables
Commonwealth Fusion Systems operating metrics behind the KPI charts, newest period first (up to 24 periods per chart). Periods use each company's own fiscal labels where the source does; each table names its source.
| Period | Field (Tesla) |
|---|---|
| 2023-Q3 TF coil 1 | 20 |
| 2021-09 TFMC | 20 |
Source: src/data/kpis/commonwealth-fusion-systems/hts-magnet-performance-milestones.json
Frequently asked questions
What does Commonwealth Fusion Systems do?
MIT-spinout developer of the SPARC compact tokamak and the ARC power plant (about 400 MWe, planned in Chesterfield County, VA). High-temperature superconducting (HTS) magnet leader. Raised $4B in total (CFS, Jul 30 2026), including a more than $1.8B Series B in Dec 2021 led by Tiger Global and an $863M Series B2 on Aug 28 2025. SPARC Q>1 target 2027; Devens MA construction ongoing. Commonwealth Fusion Systems was founded in 2018, is headquartered in Devens, MA and employs ~1,000.
How much funding has Commonwealth Fusion Systems raised?
Commonwealth Fusion Systems has raised $4B (CFS, Jul 30 2026) in total, based on the funding rounds Sterling tracks.
Who are Commonwealth Fusion Systems's main competitors?
Sterling groups Commonwealth Fusion Systems in the Nuclear industry, alongside Helion Energy (private), TAE Technologies (private), Tokamak Energy (private), Pacific Fusion (private) and General Fusion (private).
If I'm investing in Commonwealth Fusion Systems, what similar companies should I consider?
If you are researching Commonwealth Fusion Systems, also look at Helion Energy (private), TAE Technologies (private) and Tokamak Energy (private). You can browse the full Nuclear industry on Sterling.