Partial operating KPIs

This page has 3 company-specific operating KPI charts. A sourced floor is 4. Sector membership does not count.

CFS SPARC HTS Toroidal Field Achieved

Line chart: CFS SPARC HTS Toroidal Field Achieved for Commonwealth Fusion Systems. 2021-09 TFMC-2023-Q3 TF coil 1, values in tesla. 2021-09 TFMC 50%, 2023-Q3 TF coil 1 50%.
Field (Tesla)

Commonwealth Fusion Systems: HTS Magnet Performance Milestones

Table: Commonwealth Fusion Systems: HTS Magnet Performance Milestones for Commonwealth Fusion Systems. 12 rows across Milestone, Date, Field Strength Achieved, Significance.
MilestoneDateField Strength AchievedSignificance
SPARC TFMC demonstration (industry-first commercial HTS tokamak magnet)2021-0920 Tesla at 20 KNature paper Sep 2021; validated REBCO architecture at commercial scale; opened HTS-tokamak path
MIT PSFC + CFS HTS tape supply chain build-out2022-Q2 to 2023-Q4N/A (manufacturing capacity scaling)Established stable REBCO tape supply via Faraday Factory + Fujikura + AMSC + others
SPARC TF Coil #1 manufactured + factory-tested2023-Q3Confirmed 20+ T performance at full coil scaleFirst production TF coil at full SPARC scale (~10 m tall)
SPARC TF Coil #2-6 manufactured + tested2023-Q4 to 2024-Q4Confirmed performance per designScaling magnet production cadence through factory
SPARC TF Coil #7-12 production2025-Q2 to 2025-Q4Performance per designContinued production cadence
First production D-shaped TF coils validated (DOE review)2025-09Met design specifications per DOE review boardMonth-long test campaign; DOE national-lab magnet specialists confirmed the data, triggering an $8M Milestone-Based Fusion Development Program payment, the largest first-phase award of the eight participating companies
TF1 installed in SPARC tokamak hall (Devens MA)2025-2026CompleteFirst of 18 toroidal field magnets installed; most tangible hardware milestone on the path to first plasma
SPARC TF Coil set complete (all 18 coils)Target 2026-Q1Performance per designRequired for SPARC mechanical complete + first plasma
Central solenoid + poloidal field coils completeTarget 2026-Q3Performance per designFinal magnet subsystems before SPARC first plasma
ARC commercial magnet design freezeTarget 2028Higher field strength + duty cycle vs SPARCARC commercial scale-up; design improvements over SPARC magnets
ARC magnet production beginsTarget 2029Performance per ARC designFollowing SPARC operational validation
Editorial. Why this mattersHTS magnets are the structural enabler of compact + commercial-scale fusion tokamaks. CFS's 2021 TFMC demonstration established the company-unique competitive lead. Marquee question: does CFS maintain its HTS magnet lead vs Tokamak Energy (the only comparable HTS tokamak developer) + emerging Chinese + European programs, or does the HTS supply chain mature enough that the lead narrows?

Commonwealth Fusion Systems: SPARC Construction Progress at Devens MA

Table: Commonwealth Fusion Systems: SPARC Construction Progress at Devens MA for Commonwealth Fusion Systems. 11 rows across Subsystem, Status, Milestone Date, Significance.
SubsystemStatusMilestone DateSignificance
Devens MA campus + tokamak hallOperational2023-Q3Tokamak hall fully constructed; supporting facilities operational
HTS magnet manufacturing (Tokamak Field Magnet Coils)TFMC SPARC demonstration successful 20212021-09 (TFMC 20 T at 20 K)Industry-first commercial-scale HTS tokamak magnet; validated REBCO architecture
Central solenoid assemblyManufacturing in progress at supplierOn track for 2025 deliveryREBCO-based; combined with TF coils provides plasma confinement
Vacuum vessel fabricationManufacturing in progress at supplierOn track for 2025-2026 deliveryFirst-wall + neutron shielding integrated
Toroidal Field (TF) coil set productionFirst 6 of 18 TF coils complete + testedProduction target complete 2026-Q1Each TF coil ~10 m tall + ~1.5 m wide; HTS REBCO tape
Plasma diagnostics + control systemsDesign phase complete; supplier procurement in progressTarget operational 2026-Q3Real-time plasma control + diagnostics for Q > 1 demonstration
SPARC first plasma (mechanical complete)Target 2026-Q4 to 2027-Q1On schedule (revised from original 2025 target)Original Series B 2021 target was 2025; current target 2026 to 2027 H1
SPARC Q > 1 net energy gain demonstrationTarget 2027 (revised from 2026)On schedule per current commercial roadmapThe scientific milestone; required for ARC commercial commitments
ARC commercial design freeze (Virginia)Target 2028Design work in progress alongside SPARC operationsGoogle ARC Virginia PPA (Jun 2025; 200 MW) anchored on this milestone
ARC FOAK commercial operation (Virginia)Target 2030On schedule per Series B + Series B2 roadmapsMarquee commercial-fusion target; on schedule vs original announcement
Editorial. Why this mattersCFS + SPARC is the most aggressive credible commercial-fusion timeline + the only fusion developer with a binding commercial PPA tied to demonstration timelines (Google + ARC, Jun 2025). HTS magnet technology is the company-unique enabler. Marquee question: does SPARC achieve Q > 1 on schedule (2027) + does that validate the broader HTS-tokamak path that ARC depends on?
Commonwealth Fusion Systems in Nuclear cover

Commonwealth Fusion Systems in Nuclear

KPI data tables

Commonwealth Fusion Systems operating metrics behind the KPI charts, newest period first (up to 24 periods per chart). Periods use each company's own fiscal labels where the source does; each table names its source.

CFS SPARC HTS Toroidal Field Achieved (tesla)
PeriodField (Tesla)
2023-Q3 TF coil 120
2021-09 TFMC20

Source: src/data/kpis/commonwealth-fusion-systems/hts-magnet-performance-milestones.json

Ask Sterling

Register for a premium account to gain access to Sterling AI.

Get Started

Things you can ask Sterling:

Summarize Tesla's latest earnings reportWhy did NVIDIA's margins expand?Compare Apple vs Microsoft's cash flowWhat's driving EV industry growth?
Menu
Favorites
Commonwealth Fusion Systems - KPIs | Sterling