| Hermes construction permit (NRC) | 2023 stated | Achieved December 2023 | Complete (first US non-LWR construction permit) |
| Hermes site construction begun (Oak Ridge TN) | 2023-Q4 | Achieved 2023-Q4 | Complete; construction continuing |
| Hermes 1 safety-related nuclear construction begun | 2025 | Complete (May 1, 2025) | Formal start of safety-related nuclear construction after excavation finished Oct 2024 |
| Hermes mechanical completion | 2026-Q3 | Slipped: Kairos now expects construction complete in 2028 | NRC extended the latest completion date from Dec 31 2026 to Apr 30 2029, citing first-of-a-kind design and construction delays |
| Hermes first criticality | 2026-Q4 to 2027-Q1 | Slipped to 2028-2029 following the construction extension | Demonstration scale; not for commercial electricity |
| Hermes 2 demonstration plant groundbreaking | n/a (new milestone) | Complete: broke ground | Follow-on demonstration plant alongside Hermes 1 at Oak Ridge |
| KP-FHR design certification (NRC) | Target 2027-2028 | On schedule per current Kairos statements | Required before commercial KP-FHR LRIP |
| Google PPA announced (Oct 2024) | Up to 500 MWe across 6-7 plants 2030-2035 | Binding commercial off-take | Largest single SMR-developer PPA in industry |
| First Google KP-FHR plant COD | 2030 (Google PPA terms) | On schedule per Kairos current statements; consensus 2030-2031 | FOAK commercial plant; site TBD (likely Oak Ridge area) |
| Subsequent Google plants (2nd through 6-7) | 2031-2035 stated cadence | On schedule per Kairos current statements; consensus 2031-2035 | Each plant 70 MWe to ~150 MWe depending on configuration |
| TVA partnership (announced 2024) | Multi-plant deployment study | Operationalized: TVA power purchase agreement signed Aug 2025 | The Google 500 MWe agreement is delivered through TVA, converting the framework into a contracted offtake route |
| TRISO-X partnership (X-energy) | TRISO fuel supply for KP-FHR commercial plants | Active partnership; fuel supply from Oak Ridge TRISO-X facility 2027+ | TRISO-X facility under construction (X-energy) |
| Editorial. Why this matters | | | Kairos achieved the first US non-LWR construction permit (Dec 2023), validating the regulatory path for advanced fluoride-salt reactors. The Google PPA (Oct 2024) is the largest commercial off-take commitment to any SMR developer. Marquee question: does Kairos deliver Hermes (2026-2027) + first Google KP-FHR plant (2030) on schedule, validating the full advanced-reactor commercial path, or does any slip cascade through the 6-7 plant Google deployment + reset the broader SMR commercialization narrative? |