Partial operating KPIs

This page has 3 company-specific operating KPI charts. A sourced floor is 4. Sector membership does not count.

TerraPower Disclosed Private Round Sizes

Line chart: TerraPower Disclosed Private Round Sizes for TerraPower. 2022 equity raise-2025-06 NVentures round, values in usd_millions. 2022 equity raise 56%, 2025-06 NVentures round 44%.
Round size ($M)

TerraPower: Funding Rounds + Capital Stack

Table: TerraPower: Funding Rounds + Capital Stack for TerraPower. 8 rows across Round, Date, Amount, Lead Investors, Notes.
RoundDateAmountLead InvestorsNotes
DOE ARDP Phase 1 award (Natrium)Oct 2020$80M (initial)DOE Office of Nuclear EnergySelected alongside X-energy as one of two ARDP demonstration awardees; DOE planned $3.2B over seven years for the two projects, subject to appropriations
Equity raise (first phase Aug 2022)Aug 15 2022A minimum of $750MSK Inc. and SK Innovation (SK invested $250M) and Bill Gates co-ledFurther terms not disclosed (TerraPower, Aug 15 2022)
Equity raise (concluded Nov 2022)Nov 3 2022$830M total ($750M first phase plus $80M)Additional investors include ArcelorMittal (XCarb Innovation Fund) and Korea Shipbuilding & Offshore EngineeringTerraPower called it the largest private raise among advanced nuclear companies (TerraPower, Nov 3 2022)
DOE funding plan for NatriumNov 16 2021Nearly $2B plannedDOE Office of Nuclear EnergySubject to appropriations (DOE, Nov 16 2021)
$650M fundraise (NVIDIA venture arm)Jun 18 2025$650MNVentures (NVIDIA) as a new investor; Bill Gates and HD Hyundai are current investorsFurther terms not disclosed (TerraPower, Jun 18 2025)
KHNP joins the investor baseJan 20 2026Amount not disclosedKorea Hydro & Nuclear Power (KHNP)KHNP's first investment in an advanced nuclear company; it joins SK as an investor (TerraPower, Jan 20 2026)
Equity raises printed, 2022 and 20252022 and 2025$1.48B ($830M + $650M)Sum of the two amounts TerraPower printsFounder funding and the terms of other rounds are not printed
Editorial. Why this mattersTerraPower's printed financing is two equity raises ($830M in 2022, $650M in 2025), KHNP's 2026 investment and DOE's plan to invest nearly $2B in Natrium, subject to appropriations. Marquee question: does that funding carry the company through completion of Kemmerer Unit 1, which TerraPower expects in 2030, or does another raise close mid-construction?

TerraPower: Natrium Kemmerer Wyoming Construction Permit + COD Timeline

Table: TerraPower: Natrium Kemmerer Wyoming Construction Permit + COD Timeline for TerraPower. 13 rows across Milestone, Target Date, Status, Notes.
MilestoneTarget DateStatusNotes
NRC pre-application engagement2020-2022CompleteInitial NRC docket interactions; design framing
Site selection (Kemmerer WY)Nov 2021CompleteAnnounced Nov 16 2021; near the retiring Naughton coal plant; PacifiCorp partner
NRC Construction Permit Application (CPA) submitted2024-Q1Complete (March 2024)Filed under 10 CFR Part 50 (vs Part 52 combined license)
Non-nuclear site construction begun2024-Q2Complete (Jun 10 2024)Start of construction marked Jun 10 2024; non-nuclear construction starts first and nuclear construction follows NRC approval
NRC CPA technical review continuing2024-2025Complete (Dec 2025)NRC completed its safety review in Dec 2025 (DOE, Mar 9 2026); TerraPower says the review was completed in 18 months
NRC Construction Permit issuedTarget 2026-Q1Complete (Commission decision Mar 4 2026; permit CPAR-1 issued Mar 9 2026, 91 FR 12628)First construction permit ever issued by the NRC for a commercial non-light-water power reactor (DOE, Mar 9 2026)
Construction start (Kemmerer Unit 1)Target 2026-Q2Complete: construction began Apr 23 2026 (TerraPower)TerraPower expects Kemmerer Unit 1 to be completed in 2030 (TerraPower, Aug 31 2026)
Operating License Application submittedTarget 2028Subject to construction progressSeparate from CP; TerraPower anticipates submitting the application in 2028 (Natrium FAQ)
Sodium Test and Fill (STF) facility completeTarget 2027-Q4Under construction at siteIndustrial-scale sodium handling + testing facility
Fuel load (HALEU)No date publishedSubject to construction + OL + HALEU supply chainHALEU supplied by Centrus + DOE consortium
First criticalityNo date publishedSubject to fuel load + commissioningTerraPower expects the plant to be completed in 2030 and gives no criticality date (Aug 31 2026)
Plant completion (Kemmerer Unit 1)Expected 2030Under construction since Apr 23 2026TerraPower expects Kemmerer Unit 1 to be completed in 2030 (TerraPower, Aug 31 2026)
Editorial. Why this mattersNatrium at Kemmerer is the marquee FOAK advanced-reactor construction project + the largest single DOE ARDP-funded demonstration. The sodium-cooled fast-reactor + thermal-storage architecture is uniquely Natrium among advanced reactor designs. Marquee question: does Kemmerer Unit 1 reach completion in 2030 as TerraPower expects, validating the broader SFR + thermal-storage commercial path, or does any slip cascade through the broader advanced-reactor commercialization narrative?
TerraPower in Nuclear cover

TerraPower in Nuclear

KPI data tables

TerraPower operating metrics behind the KPI charts, newest period first (up to 24 periods per chart). Periods use each company's own fiscal labels where the source does; each table names its source.

TerraPower Disclosed Private Round Sizes (usd_millions)
PeriodRound size ($M)
2025-06 NVentures round650
2022 equity raise830

Source: src/data/kpis/terrapower/funding-rounds-table.json

Ask Sterling

Register for a premium account to gain access to Sterling AI.

Get Started

Things you can ask Sterling:

Summarize Tesla's latest earnings reportWhy did NVIDIA's margins expand?Compare Apple vs Microsoft's cash flowWhat's driving EV industry growth?
Menu
Favorites
TerraPower - KPIs | Sterling