Partial operating KPIs
This page has 3 company-specific operating KPI charts. A sourced floor is 4. Sector membership does not count.
TerraPower Disclosed Private Round Sizes
TerraPower: Funding Rounds + Capital Stack
| Round | Date | Amount | Lead Investors | Notes |
|---|---|---|---|---|
| DOE ARDP Phase 1 award (Natrium) | Oct 2020 | $80M (initial) | DOE Office of Nuclear Energy | Selected alongside X-energy as one of two ARDP demonstration awardees; DOE planned $3.2B over seven years for the two projects, subject to appropriations |
| Equity raise (first phase Aug 2022) | Aug 15 2022 | A minimum of $750M | SK Inc. and SK Innovation (SK invested $250M) and Bill Gates co-led | Further terms not disclosed (TerraPower, Aug 15 2022) |
| Equity raise (concluded Nov 2022) | Nov 3 2022 | $830M total ($750M first phase plus $80M) | Additional investors include ArcelorMittal (XCarb Innovation Fund) and Korea Shipbuilding & Offshore Engineering | TerraPower called it the largest private raise among advanced nuclear companies (TerraPower, Nov 3 2022) |
| DOE funding plan for Natrium | Nov 16 2021 | Nearly $2B planned | DOE Office of Nuclear Energy | Subject to appropriations (DOE, Nov 16 2021) |
| $650M fundraise (NVIDIA venture arm) | Jun 18 2025 | $650M | NVentures (NVIDIA) as a new investor; Bill Gates and HD Hyundai are current investors | Further terms not disclosed (TerraPower, Jun 18 2025) |
| KHNP joins the investor base | Jan 20 2026 | Amount not disclosed | Korea Hydro & Nuclear Power (KHNP) | KHNP's first investment in an advanced nuclear company; it joins SK as an investor (TerraPower, Jan 20 2026) |
| Equity raises printed, 2022 and 2025 | 2022 and 2025 | $1.48B ($830M + $650M) | Sum of the two amounts TerraPower prints | Founder funding and the terms of other rounds are not printed |
| Editorial. Why this matters | TerraPower's printed financing is two equity raises ($830M in 2022, $650M in 2025), KHNP's 2026 investment and DOE's plan to invest nearly $2B in Natrium, subject to appropriations. Marquee question: does that funding carry the company through completion of Kemmerer Unit 1, which TerraPower expects in 2030, or does another raise close mid-construction? |
TerraPower: Natrium Kemmerer Wyoming Construction Permit + COD Timeline
| Milestone | Target Date | Status | Notes |
|---|---|---|---|
| NRC pre-application engagement | 2020-2022 | Complete | Initial NRC docket interactions; design framing |
| Site selection (Kemmerer WY) | Nov 2021 | Complete | Announced Nov 16 2021; near the retiring Naughton coal plant; PacifiCorp partner |
| NRC Construction Permit Application (CPA) submitted | 2024-Q1 | Complete (March 2024) | Filed under 10 CFR Part 50 (vs Part 52 combined license) |
| Non-nuclear site construction begun | 2024-Q2 | Complete (Jun 10 2024) | Start of construction marked Jun 10 2024; non-nuclear construction starts first and nuclear construction follows NRC approval |
| NRC CPA technical review continuing | 2024-2025 | Complete (Dec 2025) | NRC completed its safety review in Dec 2025 (DOE, Mar 9 2026); TerraPower says the review was completed in 18 months |
| NRC Construction Permit issued | Target 2026-Q1 | Complete (Commission decision Mar 4 2026; permit CPAR-1 issued Mar 9 2026, 91 FR 12628) | First construction permit ever issued by the NRC for a commercial non-light-water power reactor (DOE, Mar 9 2026) |
| Construction start (Kemmerer Unit 1) | Target 2026-Q2 | Complete: construction began Apr 23 2026 (TerraPower) | TerraPower expects Kemmerer Unit 1 to be completed in 2030 (TerraPower, Aug 31 2026) |
| Operating License Application submitted | Target 2028 | Subject to construction progress | Separate from CP; TerraPower anticipates submitting the application in 2028 (Natrium FAQ) |
| Sodium Test and Fill (STF) facility complete | Target 2027-Q4 | Under construction at site | Industrial-scale sodium handling + testing facility |
| Fuel load (HALEU) | No date published | Subject to construction + OL + HALEU supply chain | HALEU supplied by Centrus + DOE consortium |
| First criticality | No date published | Subject to fuel load + commissioning | TerraPower expects the plant to be completed in 2030 and gives no criticality date (Aug 31 2026) |
| Plant completion (Kemmerer Unit 1) | Expected 2030 | Under construction since Apr 23 2026 | TerraPower expects Kemmerer Unit 1 to be completed in 2030 (TerraPower, Aug 31 2026) |
| Editorial. Why this matters | Natrium at Kemmerer is the marquee FOAK advanced-reactor construction project + the largest single DOE ARDP-funded demonstration. The sodium-cooled fast-reactor + thermal-storage architecture is uniquely Natrium among advanced reactor designs. Marquee question: does Kemmerer Unit 1 reach completion in 2030 as TerraPower expects, validating the broader SFR + thermal-storage commercial path, or does any slip cascade through the broader advanced-reactor commercialization narrative? |

TerraPower in Nuclear
KPI data tables
TerraPower operating metrics behind the KPI charts, newest period first (up to 24 periods per chart). Periods use each company's own fiscal labels where the source does; each table names its source.
| Period | Round size ($M) |
|---|---|
| 2025-06 NVentures round | 650 |
| 2022 equity raise | 830 |
Source: src/data/kpis/terrapower/funding-rounds-table.json