Electricity Load Growth by Utility

US Electricity Demand, 1990 to 2026

Annual US net generation in TWh: four decades of growth, a fifteen-year plateau from 2007, and the record-setting inflection now underway. 2025 is EIA's preliminary total and 2026 is an EIA projection.

Retail Sales by Customer Class

Who is buying the new kilowatt-hours. Commercial sales, the class that includes most data-center load, closed to within 16 TWh of residential in 2025: 1,503 TWh versus 1,519 TWh.

Five-Year Peak Demand Forecast Revisions

The same question, asked three years in a row: how much will US peak demand grow over the next five years? Grid planner forecasts compiled by Grid Strategies roughly quintupled between 2022 and 2024.

By year the forecast was compiled.

Data-Center Share of US Electricity

Data centers took about 4.4% of US electricity in 2023, up from 1.9% in 2018. LBNL's June 2026 update puts 2030 at 11.8%, with scenarios from 9.5% to 15.3%, a wide band that is itself the story: nobody knows how big the wedge gets.

Interconnection Queues by Resource

Roughly 2.6 TW of generation and storage waited in US interconnection queues at the end of 2023, more than twice the installed US fleet. Solar and storage dominate; historically most queued capacity never gets built.

Utility-Disclosed Large-Load Pipelines

What roster utilities say is coming, in their own numbers. Definitions differ by company (signed commitments vs interconnection requests vs planning pipelines), so rows are not comparable with each other.

Dominion EnergyD

~40 GW

Data-center capacity in substation planning or construction phases across its contracting pipeline (December 2024 disclosure)

Virginia

American Electric PowerAEP

>20 GW

Signed customer commitment letters for incremental load by the end of the decade, concentrated in Ohio, Texas, and Indiana

Ohio, Texas, Indiana

American Electric PowerAEP

69 GW

Q2 2026: total contracted load growth through 2030 under signed load agreements with hyperscalers, data centers and industrials; up from 56 GW (Q4 2025 release) and 63 GW (Q1 2026 release). A wider, redefined basis than the signed-commitment-letter row above

AEP footprint, primarily Texas

PPL CorporationPPL

>10 GW

Data-center interconnection requests in advanced stages in its Pennsylvania service territory

Pennsylvania (PJM)

PPL CorporationPPL

31.8 GW

Q2 2026: PPL Electric Utilities data-center pipeline in advanced stages of planning (same basis as the row above), of which over 11 GW is under signed electric service agreements and more than 6.5 GW is under construction

Pennsylvania (PJM)

Southern CompanySO

~8 GW

Georgia Power incremental load pipeline through the mid-2030s, most of it large load, per Georgia PSC filings

Georgia

Southern CompanySO

~16 GW

Q2 2026: contracts signed since 2023 with new data centers and other large-load customers, each over 100 MW: about 11 GW reviewed by state commissions plus about 5 GW agreed and awaiting review. Ramps over several years, service through 2028. Covers all three traditional electric operating companies, wider than the Georgia-only row above

Georgia, Alabama, Mississippi

EntergyETR

>2 GW

Meta's Richland Parish campus alone; Entergy is building roughly 2.3 GW of new gas generation approved for it in late 2025

Louisiana

WEC Energy GroupWEC

>1.8 GW

Expected data-center demand in southeast Wisconsin anchored by Microsoft's Mount Pleasant campus

Wisconsin

EvergyEVRG

>1 GW

Announced economic development load including Panasonic's De Soto plant, Google, and Meta data-center projects

Kansas, Missouri

EvergyEVRG

~2.6 GW

2026 (Q2 10-Q): electric service agreements signed in 2026 with data-center customers, three new projects and two expansions, projected peak steady-state load of about 2,600 MW, service from 2026 to 2028. Signed agreements, not announced load

Kansas, Missouri

ExelonEXC

~11 GW

Q2 2026: 'high probability' data-center load in advanced phases of design or backed by FERC-approved transmission security agreements, about 9 GW at ComEd and about 2 GW in the Mid-Atlantic. A further ~25 GW (ComEd ~17 GW, Mid-Atlantic ~8 GW) is future pipeline within current or future cluster studies

Illinois, Mid-Atlantic (PJM)

Oncor (Sempra)SRE

298 GW

Q2 2026: Oncor's large-load interconnection queue, 737 requests: about 282 GW from data centers and over 16 GW from other industrial load. A request queue, the speculative end of the definitions spectrum, and inside ERCOT's roughly 474 GW; about 44 GW is expected to be eligible for ERCOT's Batch Zero process

Texas (ERCOT)

UtilityDisclosed figureWhat the figure counts
Dominion EnergyD~40 GWData-center capacity in substation planning or construction phases across its contracting pipeline (December 2024 disclosure)
American Electric PowerAEP>20 GWSigned customer commitment letters for incremental load by the end of the decade, concentrated in Ohio, Texas, and Indiana
American Electric PowerAEP69 GWQ2 2026: total contracted load growth through 2030 under signed load agreements with hyperscalers, data centers and industrials; up from 56 GW (Q4 2025 release) and 63 GW (Q1 2026 release). A wider, redefined basis than the signed-commitment-letter row above
PPL CorporationPPL>10 GWData-center interconnection requests in advanced stages in its Pennsylvania service territory
PPL CorporationPPL31.8 GWQ2 2026: PPL Electric Utilities data-center pipeline in advanced stages of planning (same basis as the row above), of which over 11 GW is under signed electric service agreements and more than 6.5 GW is under construction
Southern CompanySO~8 GWGeorgia Power incremental load pipeline through the mid-2030s, most of it large load, per Georgia PSC filings
Southern CompanySO~16 GWQ2 2026: contracts signed since 2023 with new data centers and other large-load customers, each over 100 MW: about 11 GW reviewed by state commissions plus about 5 GW agreed and awaiting review. Ramps over several years, service through 2028. Covers all three traditional electric operating companies, wider than the Georgia-only row above
EntergyETR>2 GWMeta's Richland Parish campus alone; Entergy is building roughly 2.3 GW of new gas generation approved for it in late 2025
WEC Energy GroupWEC>1.8 GWExpected data-center demand in southeast Wisconsin anchored by Microsoft's Mount Pleasant campus
EvergyEVRG>1 GWAnnounced economic development load including Panasonic's De Soto plant, Google, and Meta data-center projects
EvergyEVRG~2.6 GW2026 (Q2 10-Q): electric service agreements signed in 2026 with data-center customers, three new projects and two expansions, projected peak steady-state load of about 2,600 MW, service from 2026 to 2028. Signed agreements, not announced load
ExelonEXC~11 GWQ2 2026: 'high probability' data-center load in advanced phases of design or backed by FERC-approved transmission security agreements, about 9 GW at ComEd and about 2 GW in the Mid-Atlantic. A further ~25 GW (ComEd ~17 GW, Mid-Atlantic ~8 GW) is future pipeline within current or future cluster studies
Oncor (Sempra)SRE298 GWQ2 2026: Oncor's large-load interconnection queue, 737 requests: about 282 GW from data centers and over 16 GW from other industrial load. A request queue, the speculative end of the definitions spectrum, and inside ERCOT's roughly 474 GW; about 44 GW is expected to be eligible for ERCOT's Batch Zero process

Where the New Demand Comes From

Modeled decomposition of incremental US consumption by 2028: data centers dominate the near-term wedge, with manufacturing reshoring and the electrification of transport and buildings as the slower second leg.

Commercial Sales Growth in Data-Center States

Delivered commercial kilowatt-hours, 2023 versus 2024. Nevada, Arizona, Ohio, Pennsylvania, Georgia, and Virginia posted the largest jumps among major roster states. Texas commercial was flat; the Texas increase landed in industrial.

Ask Sterling

Register for a premium account to gain access to Sterling AI.

Get Started

Things you can ask Sterling:

Summarize Tesla's latest earnings reportWhy did NVIDIA's margins expand?Compare Apple vs Microsoft's cash flowWhat's driving EV industry growth?
Menu
Favorites
US Electricity Load Growth Forecasts by Utility (2026) | Sterling