Utility Regulation & Affordability

Average Allowed ROE Over Time

Estimate, not company-reported, for the 1985 point (S&P RRA annual averages begin in 1990). The return commissions actually grant, from roughly 15% in the mid-1980s to roughly 9.7% in 2024. The four-decade slide tracked falling rates; the recent upturn is commissions partially catching up to the higher-rate environment.

Rate Case Activity

Estimate, not company-reported: S&P RRA publishes total decision counts but no free general-rate-case series, so these counts are our approximation. Completed general rate cases per year. Filing activity sits at historically high levels because capex outruns approved rates: spend ahead of your last case and you under-earn until the next one resets them.

Electricity Prices vs Headline Inflation

Both indexed to 100 in 2019.

Both indexed to 100 in 2019. Electricity tracked headline through 2021, jumped past it in 2022, and kept climbing as headline cooled: up 37 percent by 2025 against 26 percent for all items. That widening gap is the political constraint on the buildout.

Residential Electricity Prices by State

2025 average residential prices for a selection of states spanning the national range, with the roster utility serving each. Prices reflect fuel mix, geography, and policy costs, not utility efficiency alone.

Average Monthly Residential Bill by State

Price times usage: Hawaii and Connecticut are expensive per kWh, Alabama and Texas are high-bill because homes use more. The US average was $151 a month in 2025.

The dashed line is the US average of $151 a month. High bills can come from high prices (Hawaii, Connecticut) or high usage (Alabama, Texas).

Large-Load Tariff Scorecard

How states are making data centers pay their own way: minimum-take provisions, long contract terms, collateral, and exit fees, all aimed at shifting stranded-asset risk off other ratepayers.

Ohio

AEP Ohio

Approved 2025

Dedicated data-center tariff class with minimum demand charges (a large share of contracted capacity billed whether used or not), multi-year terms, collateral requirements, and exit fees

Texas

ERCOT-wide (statute, PUCT rule, governor directive)

SB 6 enacted June 2025; Batch Zero approved 18 Jun 2026; verification hold from 3 Aug 2026

SB 6 created a large-load interconnection framework with curtailment obligations, disclosure of duplicate requests, and cost responsibility for transmission upgrades. On 18 June 2026 the PUCT approved ERCOT's Batch Zero process, which studies qualified loads of 75 MW or more as one batch. On 3 August 2026 Governor Abbott's letter directed ERCOT to verify data-center projects before advancing any through interconnection; ERCOT postponed its 7 August Batch Zero classification notices and said it would seek a good-cause exception at the PUCT's 20 August meeting

Georgia

Georgia Power (SO)

Rules adopted 2025

Large-load rules with minimum billing terms and creditworthiness standards for loads above 100 MW, plus IRP treatment of new large loads

Virginia

Dominion (D)

SCC final order 31 Jul 2026 (Rider T1)

The SCC directed Dominion to file, in a new docket (PUR-2026-00131, opened 25 Aug 2026), an amended line extension policy requiring a mandatory contribution in aid of construction for defined direct-connect transmission facilities serving large loads, due within 90 days of the order. The order also approved a cost-allocation forecast adjustment and the 85 percent transmission minimum demand charge for certain large-load customers from 1 January 2027

Indiana

NiSource, AES Indiana

Approved 2024 to 2025

Settlements requiring 80 percent minimum take, roughly 10 to 20 year terms, and collateral from large-load customers

PJM (federal)

Multi-state

FERC order December 2025

Co-location proceeding addressing how behind-the-meter and co-located large loads pay for grid services they use

Pennsylvania

State permitting (Executive Order 2026-05)

Executive order 18 Aug 2026

Data centers with peak demand over 25 MW must sign a DEP consent order implementing the Governor's GRID Requirements to enter the state permit review process: clean firm energy procurement scaling from 10 percent to 32 percent by 2035, and the developer pays 100 percent of the costs its project causes

Federal (House)

State utility commissions

H.R. 9340 passed the House 417 to 3 on 16 Sep 2026

Ratepayer Protection Act: state utility commissions would consider large-load standards for data centers drawing more than 100 MW, so that they pay the full incremental cost of serving their loads, using PURPA section 111(d)

Federal (NERC)

Computational load owners, transmission planners and owners

Final ballot concluded 14 Oct 2026; to go to the NERC Board of Trustees for adoption

Project 2026-02 standards CLO-001-1, CLO-002-1 and CLO-003-1 plus revised FAC-001-5 and FAC-002-5: interconnection studies and modeling data, operational data and communications, and protection coordination and disturbance monitoring, for computational load sites of 50 MW or more supplied at 100 kV or above

JurisdictionKey terms
Ohio
AEP Ohio
Dedicated data-center tariff class with minimum demand charges (a large share of contracted capacity billed whether used or not), multi-year terms, collateral requirements, and exit fees
Texas
ERCOT-wide (statute, PUCT rule, governor directive)
SB 6 created a large-load interconnection framework with curtailment obligations, disclosure of duplicate requests, and cost responsibility for transmission upgrades. On 18 June 2026 the PUCT approved ERCOT's Batch Zero process, which studies qualified loads of 75 MW or more as one batch. On 3 August 2026 Governor Abbott's letter directed ERCOT to verify data-center projects before advancing any through interconnection; ERCOT postponed its 7 August Batch Zero classification notices and said it would seek a good-cause exception at the PUCT's 20 August meeting
Georgia
Georgia Power (SO)
Large-load rules with minimum billing terms and creditworthiness standards for loads above 100 MW, plus IRP treatment of new large loads
Virginia
Dominion (D)
The SCC directed Dominion to file, in a new docket (PUR-2026-00131, opened 25 Aug 2026), an amended line extension policy requiring a mandatory contribution in aid of construction for defined direct-connect transmission facilities serving large loads, due within 90 days of the order. The order also approved a cost-allocation forecast adjustment and the 85 percent transmission minimum demand charge for certain large-load customers from 1 January 2027
Indiana
NiSource, AES Indiana
Settlements requiring 80 percent minimum take, roughly 10 to 20 year terms, and collateral from large-load customers
PJM (federal)
Multi-state
Co-location proceeding addressing how behind-the-meter and co-located large loads pay for grid services they use
Pennsylvania
State permitting (Executive Order 2026-05)
Data centers with peak demand over 25 MW must sign a DEP consent order implementing the Governor's GRID Requirements to enter the state permit review process: clean firm energy procurement scaling from 10 percent to 32 percent by 2035, and the developer pays 100 percent of the costs its project causes
Federal (House)
State utility commissions
Ratepayer Protection Act: state utility commissions would consider large-load standards for data centers drawing more than 100 MW, so that they pay the full incremental cost of serving their loads, using PURPA section 111(d)
Federal (NERC)
Computational load owners, transmission planners and owners
Project 2026-02 standards CLO-001-1, CLO-002-1 and CLO-003-1 plus revised FAC-001-5 and FAC-002-5: interconnection studies and modeling data, operational data and communications, and protection coordination and disturbance monitoring, for computational load sites of 50 MW or more supplied at 100 kV or above

Wildfire Liability Exposure and Shields

The tail risk the ratemaking formula never priced. California's inverse condemnation doctrine imposes liability without negligence, which drove PG&E's bankruptcy and produced the 21 billion dollar AB 1054 fund now being drawn against.

CaliforniaPG&E (PCG), Edison International (EIX), Sempra (SRE)
Liability regime
Inverse condemnation: strict liability for damage from utility equipment regardless of negligence
Shield
AB 1054 fund of about 21 billion dollars, plus a safety certification that caps shareholder exposure and shifts the burden of proof
Status
Edison drawing against the fund for January 2025 Eaton fire losses; PG&E emerged from wildfire bankruptcy in 2020
HawaiiHawaiian Electric (HE)
Liability regime
Negligence-based, but the 2023 Lahaina fire produced an existential settlement
Shield
None comparable at the time; the state has since considered fund legislation
Status
Roughly 2 billion dollars of settlement obligations funded through securitization and equity issuance
ColoradoXcel Energy (XEL)
Liability regime
Negligence-based with active litigation from the 2021 Marshall fire
Shield
No dedicated state fund
Status
Marshall fire claims proceeding; Xcel also faces Texas Panhandle (Smokehouse Creek) claims
TexasXcel Energy (XEL), others
Liability regime
Negligence-based; the 2024 Smokehouse Creek fire was the largest in state history
Shield
Securitization statutes for extraordinary costs
Status
An emerging front rather than a settled regime
OregonBerkshire's PacifiCorp (not roster)
Liability regime
Negligence-based, with large jury verdicts from the 2020 Labor Day fires
Shield
No dedicated fund
Status
Included as the clearest evidence that the risk extends beyond California
Most other statesRoster utilities outside fire country
Liability regime
Standard negligence liability with prudence review
Shield
Storm and catastrophe cost recovery through riders and securitization
Status
Wildfire is not a material tail risk in most territories

Ask Sterling

Register for a premium account to gain access to Sterling AI.

Get Started

Things you can ask Sterling:

Summarize Tesla's latest earnings reportWhy did NVIDIA's margins expand?Compare Apple vs Microsoft's cash flowWhat's driving EV industry growth?
Menu
Favorites
Utility Regulation & Affordability: Market Data | Sterling