Nuclear AI Power Demand
Hyperscaler Nuclear Deals
Every confirmed Microsoft, Amazon, Google, Meta, Oracle, and Equinix nuclear deal 2023-2026. Structure classifications (grid PPA / behind-the-meter PPA / MoU / joint development) follow press releases and 8-K filings, and signed agreements are counted apart from MoUs, joint developments and talks.
Amazon
AEP + X-energy (Indiana)
960 MW
2026-10-19
- Technology
- Xe-100 SMRs (12 x 80 MW)
- Term
- n/a
- Location
- Sullivan County, Indiana
- Target start
- not disclosed
Constellation Energy
890 MW
2026-10-06
- Technology
- Existing reactor uprates (11 PJM units)
- Term
- 20 years
- Location
- Illinois, Pennsylvania, New Jersey (PJM)
- Target start
- first uprate 2028
Constellation Energy
2,700 MW
2026-10-06
- Technology
- Existing reactors (PJM fleet)
- Term
- 15 years
- Location
- PJM
- Target start
- not disclosed
Oracle
We Energies (Point Beach)
MW n/a
2026-10-02
- Technology
- Existing reactors (Point Beach 1-2, PWR)
- Term
- n/a
- Location
- Wisconsin
- Target start
- not disclosed
Amazon
Constellation Energy
690 MW
2026-09-30
- Technology
- Existing reactor + uprate (Calvert Cliffs)
- Term
- 20 years
- Location
- Calvert Cliffs, Maryland
- Target start
- uprate online 2030-2032
Georgia Power
96 MW
2026-09-21
- Technology
- Existing reactor uprates (Vogtle, Hatch)
- Term
- n/a
- Location
- Georgia
- Target start
- not disclosed
Fortum
MW n/a
2026-09-09
- Technology
- Existing reactors (Loviisa 1-2, VVER-440)
- Term
- 22 years
- Location
- Loviisa, Finland
- Target start
- 2028
Hyperscaler GW Committed by Operator
Power capacity (GW) committed to hyperscalers, aggregated by operator and broken down by counterparty. Companion to the deal-by-deal table above.
US Data Center Power Demand
US data center electricity use in TWh from Lawrence Berkeley National Laboratory's 2024 report and 2025 update, with its low and high scenarios for 2028 and 2030.
PPA Structures (deal-flow mix)
How the 23 tracked hyperscaler nuclear deals split by contract structure: power purchase agreements (10 deals, 9.3 GW) versus MoUs, joint developments, other signed agreements (commercial, prepayment, supply, master power and master plant development), talks and one deal awaiting approval (13 deals, 28.6 GW).
Power purchase agreements
9,315 MW
10 deals
MoUs and other
28,634 MW
13 deals
Nuclear Equity Performance
Monthly prices indexed to 100 on Jan 2024 versus the S&P 500, split into the eight merchant and pure-play names and the twelve regulated utilities that own most of the US reactor fleet. Markers flag the policy and deal events behind the largest moves.
TLN
480
OKLO
438
VST
363
NNE
305
LEU
264
SMR
252
CEG
220
CCJ
206
One scale. Sep 2026 values. Grey: S&P 500 (161).
Grid Interconnect Queue
Pending and decided FERC and ISO interconnection filings for nuclear-adjacent large-load data center sites, including the precedent-setting Susquehanna case.
Tracked
11
queue entries
Total MW
5,806
requested capacity
Active / approved
5,026
MW moving forward
Rejected
480
MW blocked
ERCOT
1 filingComanche Peak Nuclear Power Plant (Glen Rose, TX)
Vistra Corp
1,200 MW
ERCOT does not face FERC ISA review for BTM (out of FERC jurisdiction); state PUC review only. Vistra 8-K Sep 29 2025 disclosed a 20-year power purchase agreement (with options to extend for up to an additional 20 years) to supply 1,200 MW of carbon-free power from Comanche Peak, with delivery beginning in the fourth quarter of 2027 and ramping to full capacity by 2032; counterparty named as Amazon Web Services in Vistra's Q4 2025 earnings release (Feb 26 2026).
INR-2024-XXXX (inferred), Large load interconnection
FERC (multi-ISO)
1 filingMISO
1 filingPJM
6 filingsSusquehanna Steam Electric Station (Salem Township, PA)
PJM + Talen + Amazon
480 MW
FERC ALJ rejected Nov 1, 2024 (split decision); cost-shift to PJM ratepayers cited
ER24-2172, ISA amendment (large load co-located)
Susquehanna SES
PJM + Talen + Amazon
300 MW
Restructured to grid-network service; FERC accepted 2025-Q3
ER25-1093, Co-location service agreement (refiled)
Three Mile Island Unit 1 / Crane Clean Energy Center
Constellation
835 MW
PJM transition study in progress for return-to-service interconnection
AE2-XXX (Exelon transition), Large load interconnection
Clinton Power Station
Constellation
1,121 MW
License renewal application filed; interconnection upgrades minimal (existing capacity)
(public summary, individual ID redacted), Generator interconnection (restart support)
Byron Generating Station, IL
Constellation
110 MW
Uprate study underway; targets ~55 MW per unit
PJM transition (FY 2026 cycle, position inferred), Generator interconnection (uprate)